Habitō construction update January 2018
Block A of the development is well under way with the second to third floor columns, core walls, staircase and balconies completed. The third-floor rebar is currently in progress in preparation for concrete pour on the 22nd January. Blockwork to the ground floor of Block A has commenced, which will continue floor by floor. Following … Continue reading Habitō construction update January 2018 →