The Printworks construction update August 2018

The three Mews Houses are now complete finalising this exclusive private enclave. The under croft that leads from the pavement to the apartments and rear Mews Houses has also been prepared for final fit out with below ground services and paving complete. The ground floor bike/storage area has taken shape structurally and on completion will be available for use by residents of both the mews houses and apartments.

Progress continues within the apartment block with the fit out sequenced from the top floor down to the lower floors. Fit out materials have been stored on site ready for immediate install such as the kitchens, boilers, tiles and flooring. With first fix M&E in place throughout, the Nobilia kitchens are being installed on the top floor with the bamboo flooring also progressing throughout.