The Printworks construction update April 2018

External cladding for the apartment building is completing and scaffolding is being dismantled showcasing the external façade (see image of when complete).

Final windows to the apartments are being fitted to the first floor and fit out is due to start. Bathrooms are being fitted within the mews houses and the gardens are being prepared for landscaping.

Alexander James, Interior Designers have been on site preparing for the installation of the show house due to be ready by the end of May.