Habitō construction update May 2018

Internal and external block work is progressing to fourth and fifth floors in Block A and partitioning work and plaster boarding on the third floor is near completion.

External brickwork is complete to first floor level in Block A. Mechanical and electrical work is progressing throughout Block A. Windows have arrived and are due to be installed. Plumbers are scheduled to start, and kitchens are ready for installation. The staircase and lift shaft are complete in Block A extending to fifth floor in preparation for the steels for the penthouse apartment on the sixth floor.

Block B columns are formed with the concrete pour of the first floor now complete with the verticals started in preparation to take the third floor. The fit out of the show apartment is progressing and will soon be fitted out by Alexander James Interiors.