Habitō construction update June 2018

Block A

The show apartment is well on the way with a fully integrated Nobilia Kitchen now installed and the engineered wooden flooring has been laid in the living, dinning and kitchen areas. First fix mechanical and electrical is nearing completion.

he MVHR ducting is installed throughout the block. Internal block-work is 90-100% complete on ground, 1st, 2nd & 3rd floor and in progress 4th & 5th floor Metal Framework is complete from Ground to 5th floor except for a few small areas and the scaffold 2nd lift has been erected in all relevant areas.

Block B

Construction is advancing well. The third-floor slab is finished and the third to fourth floor columns and lift core are complete.