Habitō construction update January 2018

Block A of the development is well under way with the second to third floor columns, core walls, staircase and balconies completed. The third-floor rebar is currently in progress in preparation for concrete pour on the 22nd January. Blockwork to the ground floor of Block A has commenced, which will continue floor by floor. Following completion of the third-floor slab, third to fifth floor columns, fourth floor formwork and concrete pour will continue. The remaining reinforced concrete pads and drainage installation are to be constructed to the rear of the site creating Block B. The ground floor slab, columns and core walls of this block will begin immediately after to continue the superstructure of the build.