Habitō construction update February 2018

The structure is starting to immerse itself within the existing streetscape. The frame has now reached the 5th slab confirming the scale of Block A alone. With construction of the 5th slab ongoing, the 5th columns, stairs and lift shaft will follow immediately after. The 6th and final concrete slab will take place over the next month completing the concrete structure of Block A. The structure doesn’t end there with the penthouse steel framework to complete on top. Within the internal areas of the constructed floors, the blockwork starts to confirm the internal arrangements of the apartments.

With Block A reaching the penultimate slab, the lead in for the ground floor slab of Block B will continue with forming the rebar and concrete pour.