Habitō construction update April 2018

With the concrete frame complete on Block A, focus has been turned to Block B with the ground floor concrete slab, ground to first floor columns and first floor slab all formed.

Over the coming weeks, Block B will follow similar progression to Block A increasing to a level of four floors which will complete the superstructure.

Progress continues at pace on Block A with the external brickwork enclosing the space and reveals the style of the building. Internally within Block A, the partitions and first fix mechanical and electrical have commenced on the upper floors concurrently with the block and brick work.

Installation of the windows and kitchen of the ground floor show apartment is programmed over the next period with the fit-out and proposed interior design expected to complete with furnishings.